South Course Renovation Progress (updated Wednesday, May 26)
Medalist
Sod work continues on Holes #1, 17 and 18
Irrigation installation on hole #2 will finish this week
Bunker drainage began on hole #3 this week
Storm drainage continues on hole #5 and 6
Cal-Golf
Tee shaping and mix installation has begun on #2 and #17 tee
Rough grading has begun on hole #11

Cartpath installtion behind clubhouse Phase one cartpaths and grassing new completion Tee box construction at #2 and #17
Medalist
Sodding continues on hole #2
Irrigation installation starts on #4 latter this week
Storm drainage finishes on #6 and moves to #7 and #12 this week
Cal-Golf
Tee boxes on #3,#4 and #17 have been laser leveled and ready for sod
Rough shaping continues on hole #8
Fine grading begins on #3 today with sod to begin tomorrow

View from back of #2 green Sod installation at #2 #3 tee ready to be sodded
Medalist
Irrigation installation completed on hole 14
Cartpath installation on hole 14 will finish this week
Sod installation on hole 14 on- going
Cal- Golf
Rough shaping of hole 10 started this week
Bunker shaping on holes 15 and 16 on going
Rough shaping continues on hole #8
Final pre-seeding work completed on holes 1,18,17,2,3 and the Putting Green.
South Course Staff
Pre-plant fertility and seeding of greens 1,18,17,2,3 and the Putting Green complete
Mowing of Zoysia fairways and Bermuda grass roughs on holes 1,18,17 on- going
Topdressing of Zoysia tee’s on going

Final preparation for seeding greens Sod work begins on hole #14 South course staff top dressing tees